Home/The Process/Timeline

The process

How long it takes, and which clocks are real

Most of the timeline is the agency\u2019s to control and runs in months. Two parts of it belong to the owner and run in days.

Typical durations

Stage by stage

StageTypical durationWhose clock
Planning, route selection and reviewOne to several yearsThe agency
Title work and surveyWeeks to monthsThe agency
Notice of interest to written offerOne to six monthsThe agency
NegotiationOne month to more than a yearShared
Petition filed to answer dueDays to weeks, by stateThe owner
Deposit and possessionImmediate to a few weeks after filingThe agency
Petition to hearing or trialSix months to two yearsThe court
Judgment to paymentWeeks to monthsThe agency

These are general ranges and nothing more. A small frontage acquisition on a funded highway project can complete in months. A contested commercial taking with a disputed highest and best use can run for years.

Two different kinds of urgency

Soft dates and hard dates

Offers often carry a date, and agents sometimes say an offer will be withdrawn after it. In practice an agency that needs the property will keep negotiating, and an offer that expires is usually replaced rather than reduced. These dates are a negotiating device more often than a real limit.

Court deadlines are different. If a petition has been filed and you do not answer within the statutory period, you can lose the right to contest compensation at all, and in some states a default judgment can be entered. There is no discretion in it and no reliable way to recover afterwards.

If you are unsure which kind of date you are holding, treat it as hard until someone qualified tells you otherwise. The cost of an hour of a lawyer\u2019s time is trivial against the cost of missing a real deadline.

Questions about timing

Can I slow this down

Up to a point, and it is sometimes worth it. Negotiation takes as long as it takes, and an agency with a construction programme has its own pressure. What you cannot extend is a court deadline.

They say they need possession next month. Can they do that

In a quick take state, often yes, by depositing their estimate with the court. You can usually draw the deposit down while continuing to argue for more, but check that locally before withdrawing anything.

How long until I am actually paid

On a negotiated settlement, typically weeks after signing. On a judgment, weeks to months. Where a deposit has been made you may have access to part of it much earlier.

Not sure what to do next

Most owners are reacting to a document they did not expect. Working through it in order is easier than it looks.

Scroll to Top